Temp power permit in Rockdale County, Georgia

To get a temporary power pole (t-pole) permit in Rockdale County, you file an application with the Planning & Development through Magnet Gov permitting portal, pay the fee (typically $50–$110), and pass temporary service inspection. A temporary power pole/service to energize a site during construction — especially common on City of Atlanta jobs, which often pull it as a separate permit. Required to set a temporary service for construction before the permanent service is energized. Atlanta jobs frequently carry it alongside the general electrical permit. PullPermits.ai filing in Rockdale is on the way — join the waitlist to hear when it's live.

Permit type
Temporary Power Pole (T-Pole)
Also called
temp power, T-pole, construction power
Typical fee
$50–$110
Turnaround
2–6 business days

When it's required

When you need a temp power permit

Required to set a temporary service for construction before the permanent service is energized. Atlanta jobs frequently carry it alongside the general electrical permit.

Typical scope of work

  • Temporary pole, meter base, and disconnect
  • Grounding and weatherproofing
  • Georgia Power coordination for temporary service

Common rejection reasons

  • Pole/meter height or grounding not to spec
  • Filed under the wrong permit type
  • Not paired with the required general electrical permit

Fees

Rockdale County temp power permit fees

Residential electrical permits typically run about $50–$110, plus a 2.95% card surcharge. Rockdale adds a 2.95% card surcharge, paid to the county with the permit fee.

What a temp power permit costs in Rockdale County
ChargeAmount
Rockdale County temp power permit feeTemporary Power Pole (T-Pole) permits typically run $50–$175 (Atlanta ~$175 per permit) statewide; Rockdale lands in this range.$50–$110
Card surchargeRockdale County adds this convenience fee — you pay it to the county with the permit fee.2.95%
PullPermits.ai markup on permit feesYou pay city, county, and inspection fees directly, at exact cost — no markup, ever.$0

Figures are approximate. The city or county sets the final fee, and you pay it on its own payment page at exact cost.

Step by step

How to file a temp power permit in Rockdale County

The full process through Magnet Gov permitting portal.

  1. 1
    Confirm the jurisdiction
    Resolve the job address to Rockdale County and confirm a temporary power pole (t-pole) is the right permit type for the scope of work.
  2. 2
    Prepare credentials and forms
    Have your active Georgia electrical license, business license, and insurance on file, plus a one-time notarized save affidavit.
  3. 3
    Draft the application
    Describe the temp power scope — temporary pole, meter base, and disconnect — and attach any required documents.
  4. 4
    Review the fee preview
    Check the fee breakdown ($50–$110 in Rockdale) before anything is submitted.
  5. 5
    File the application in Magnet Gov permitting portal
    Submit the temporary power pole (t-pole) application and pay the Rockdale County fee.
  6. 6
    Track approval and schedule inspection
    Wait 2–6 business days, then book temporary service inspection.

Inspections

  • Temporary service inspection
  • Utility release

Once the permit is issued, you schedule these with Rockdale County.

Typical timeline

1–3 business days.

In Rockdale County specifically, plan on 2–6 business days.

You approve, we file

How PullPermits.ai will pull your Rockdale temp power permit

You stay the named applicant. PullPermits.ai drafts the temporary power pole (t-pole) application and files it through Magnet Gov permitting portal under your account — only after you tap approve. You pay the Rockdale County fee directly, at exact cost. Rockdale is on our rollout list; this is how it works in Atlanta today.

  1. Step 1

    Describe the job

    Tell us the Rockdale County address and the temp power scope. Your credentials are already on file.

  2. Step 2

    Review the preview

    See the full application and the fee breakdown in plain English before anything is filed.

  3. Step 3

    Tap Approve & File

    We file with Rockdale County; you pay its fee directly, at exact cost — nothing is submitted until you approve.

  4. Step 4

    Get email updates

    We track the status and email you each update until the permit is decided.

Rockdale temp power permit FAQ

How much is a temporary power pole (t-pole) permit in Rockdale County?
In Rockdale County, a temp power permit typically runs $50–$110. Residential electrical permits typically run about $50–$110, plus a 2.95% card surcharge. Rockdale County also adds a 2.95% card surcharge, paid to the county at cost. PullPermits.ai never marks up the city or county fee.
How long does a Rockdale temp power permit take?
1–3 business days. In Rockdale County specifically, expect 2–6 business days.
What inspections does a temporary power pole (t-pole) need?
Typically: Temporary service inspection, Utility release. You schedule them with Rockdale County once the permit is issued.
Anything specific about filing a temp power in Rockdale County?
Runs on Magnet Gov; requires a one-time notarized SAVE affidavit.
Why do temporary power pole (t-pole) permits get rejected?
The most common reasons: Pole/meter height or grounding not to spec; Filed under the wrong permit type; Not paired with the required general electrical permit.

Keep exploring

Working a job somewhere else? Find your jurisdiction by address or read the temp power permit guide.

Be first when Rockdale goes live

Join the waitlist and we'll tell you the day PullPermits.ai starts filing Rockdale County temporary power pole (t-pole) permits.

We’ll only email you about PullPermits going live in your area. No spam.

Try the live demoThis is an interactive demo on sample data. Nothing is really filed.