To get a temporary power pole (t-pole) permit in Cobb County, you file an application with the Community Development Agency through Accela Citizen Access (ACA), pay the fee (typically $50–$100), and pass temporary service inspection. A temporary power pole/service to energize a site during construction — especially common on City of Atlanta jobs, which often pull it as a separate permit. Required to set a temporary service for construction before the permanent service is energized. Atlanta jobs frequently carry it alongside the general electrical permit. PullPermits.ai filing in Cobb is on the way — join the waitlist to hear when it's live.
- Permit type
- Temporary Power Pole (T-Pole)
- Also called
- temp power, T-pole, construction power
- Where to file
- Accela Citizen Access (ACA)
- Typical fee
- $50–$100
- Turnaround
- 1–5 business days for over-the-counter electrical permits
When it's required
When you need a temp power permit
Required to set a temporary service for construction before the permanent service is energized. Atlanta jobs frequently carry it alongside the general electrical permit.
Typical scope of work
- Temporary pole, meter base, and disconnect
- Grounding and weatherproofing
- Georgia Power coordination for temporary service
Common rejection reasons
- Pole/meter height or grounding not to spec
- Filed under the wrong permit type
- Not paired with the required general electrical permit
Fees
Cobb County temp power permit fees
Most residential electrical permits run about $50–$100. Cobb also accepts a one-page emailed sub-contractor electrical form for the fastest path.
| Charge | Amount |
|---|---|
| Cobb County temp power permit feeTemporary Power Pole (T-Pole) permits typically run $50–$175 (Atlanta ~$175 per permit) statewide; Cobb lands in this range. | $50–$100 |
| PullPermits.ai markup on permit feesYou pay city, county, and inspection fees directly, at exact cost — no markup, ever. | $0 |
Figures are approximate. The city or county sets the final fee, and you pay it on its own payment page at exact cost.
Step by step
How to file a temp power permit in Cobb County
The full process through Accela Citizen Access (ACA).
- 1Confirm the jurisdictionResolve the job address to Cobb County and confirm a temporary power pole (t-pole) is the right permit type for the scope of work.
- 2Prepare credentials and formsHave your active Georgia electrical license, business license, and insurance on file, plus business license and proof of insurance.
- 3Draft the applicationDescribe the temp power scope — temporary pole, meter base, and disconnect — and attach any required documents.
- 4Review the fee previewCheck the fee breakdown ($50–$100 in Cobb) before anything is submitted.
- 5File the application in Accela Citizen Access (ACA)Submit the temporary power pole (t-pole) application and pay the Cobb County fee.
- 6Track approval and schedule inspectionWait 1–5 business days for over-the-counter electrical permits, then book temporary service inspection.
Inspections
- Temporary service inspection
- Utility release
Once the permit is issued, you schedule these with Cobb County.
Typical timeline
1–3 business days.
In Cobb County specifically, plan on 1–5 business days for over-the-counter electrical permits.
You approve, we file
How PullPermits.ai will pull your Cobb temp power permit
You stay the named applicant. PullPermits.ai drafts the temporary power pole (t-pole) application and files it through Accela Citizen Access (ACA) under your account — only after you tap approve. You pay the Cobb County fee directly, at exact cost. Cobb is on our rollout list; this is how it works in Atlanta today.
- Step 1
Describe the job
Tell us the Cobb County address and the temp power scope. Your credentials are already on file.
- Step 2
Review the preview
See the full application and the fee breakdown in plain English before anything is filed.
- Step 3
Tap Approve & File
We file with Cobb County; you pay its fee directly, at exact cost — nothing is submitted until you approve.
- Step 4
Get email updates
We track the status and email you each update until the permit is decided.
Cobb temp power permit FAQ
- How much is a temporary power pole (t-pole) permit in Cobb County?
- In Cobb County, a temp power permit typically runs $50–$100. Most residential electrical permits run about $50–$100. PullPermits.ai never marks up the city or county fee.
- How long does a Cobb temp power permit take?
- 1–3 business days. In Cobb County specifically, expect 1–5 business days for over-the-counter electrical permits.
- What inspections does a temporary power pole (t-pole) need?
- Typically: Temporary service inspection, Utility release. You schedule them with Cobb County once the permit is issued.
- Anything specific about filing a temp power in Cobb County?
- A one-page emailed sub-permit form is the fastest filing path; the Accela portal is the online route after.
- Why do temporary power pole (t-pole) permits get rejected?
- The most common reasons: Pole/meter height or grounding not to spec; Filed under the wrong permit type; Not paired with the required general electrical permit.
Keep exploring
All Cobb County electrical permits
Fees, portal, requirements, and every permit type for Cobb County.
Panel upgrade permit in Cobb
Replacing or upsizing a home's main electrical panel and service — the most common residential electrical permit in metro Atlanta.
EV charger permit in Cobb
Installing a Level 2 (240V) EV charging circuit — the fastest-growing residential electrical permit as EV adoption climbs.
Generator permit in Cobb
Permitting a permanently installed standby generator with an automatic transfer switch — often paired with a gas permit.
Working a job somewhere else? Find your jurisdiction by address or read the temp power permit guide.
Be first when Cobb goes live
Join the waitlist and we'll tell you the day PullPermits.ai starts filing Cobb County temporary power pole (t-pole) permits.